PERMIT #7122474-DM
1953 10TH AVE W, SEATTLE, WA
newPermit Timeline & Status
Construction Permit Timeline
Applied
March 26, 2026
In Review
1 cycle
Reviews Done
April 9, 2026
Issued
—
Completed
—
Expires
—
14
Plan Review Days — Total
14
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
In City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1953 10TH AVE W, SEATTLE, WA Property
Demolition at 1953 10TH AVE W Project
Other Seattle Neighborhood
Project Overview
Project Details
Value
N/A
Type
Residential Construction
Issued
N/A
Location
Other Seattle
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Demolish residential building per plans.
Additional Details
Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1140009
Review cycles
1
Plan review days
14
Days in corrections
0
Units added
0
Units removed
3