PERMIT #7122859-CN

2427 28TH AVE W, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 12, 2026
In Review
2 cycles
Reviews Done
May 21, 2026
Ready to Issue
May 21, 2026
Issued
May 22, 2026
Completed
Expires
November 22, 2027
129
Plan Review Days — Total
30
Plan Review Days — City Control
99
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Magnolia Neighborhood

Project Overview

Project Details
Value
$204,902
Type
Residential Construction
Issued
May 22, 2026
Location
Magnolia

Contractor Information

Contractor
BICKNELL BUILDS LLC
General Contractor
License BICKNBL824P9

Location & Map

Project Description
28th Ave W Addition Construct additions and alterations to existing one-family residence, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BICKNBL824P9
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1139768
Review cycles
2
Plan review days
129
Days in corrections
99
Expires
November 22, 2027
Open official SDCI detail →
View Contractor