PERMIT #7123032-CN

500 WALL ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 23, 2026
In Review
3 cycles
Reviews Done
June 5, 2026
Ready to Issue
June 5, 2026
Issued
June 12, 2026
Completed
Expires
133
Plan Review Days — Total
92
Plan Review Days — City Control
41
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Belltown Neighborhood

Project Overview

Project Details
Value
$560,829
Type
Residential Construction
Issued
June 12, 2026
Location
Belltown

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct non-structural interior alterations to ground and 2nd level amenity spaces for mixed-use apartment building [SKYE AT BELLTOWN]. Mechanical included.

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Multifamily
Parcel
DV0009453
Review cycles
3
Plan review days
133
Days in corrections
41
Units added
0
Units removed
0
Open Map