PERMIT #7123547-CN
3951 15TH AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 28, 2026
In Review
3 cycles
Reviews Done
March 26, 2026
Ready to Issue
March 30, 2026
Issued
March 30, 2026
Completed
—
Expires
September 30, 2027
57
Plan Review Days — Total
38
Plan Review Days — City Control
19
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$100,000
Type
Residential Construction
Issued
March 30, 2026
Location
Beacon Hill
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Qi Qi: Interior Alts Construct alterations to existing two-family dwelling, per plan
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0020526
Review cycles
3
Plan review days
57
Days in corrections
19
Expires
September 30, 2027
Existing units
2
Units added
0
Units removed
0
Sleeping rooms
0