Permit Timeline & Status

Construction Permit Timeline
Applied
May 26, 2026
In Review
1 cycle
Issued
Completed
Expires
51
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Queen Anne Neighborhood

Project Overview

Project Details
Value
$1,100,000
Type
Residential Construction
Issued
N/A
Location
Queen Anne

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
8th Ave W Townhomes Demolish existing two-family dwelling and accessory shed, per plan

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1206848
Review cycles
1
Days in corrections
51
Existing units
2
Units added
4
Units removed
2
Sleeping rooms
12