PERMIT #7124577-CN

7002 38TH AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 7, 2026
In Review
2 cycles
Reviews Done
June 12, 2026
Ready to Issue
June 12, 2026
Issued
June 12, 2026
Completed
Expires
66
Plan Review Days — Total
53
Plan Review Days — City Control
13
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ravenna Neighborhood

Project Overview

Project Details
Value
$337,107
Type
Residential Construction
Issued
June 12, 2026
Location
Ravenna

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct addition & substantial alterations to one-family dwelling per plan

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0093999
Review cycles
2
Plan review days
66
Days in corrections
13
Units added
0
Units removed
0
Open Map