PERMIT #7124696-CN

1415 6TH AVE N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 2, 2026
In Review
2 cycles
Reviews Done
May 21, 2026
Ready to Issue
May 26, 2026
Issued
May 28, 2026
Completed
Expires
49
Plan Review Days — Total
35
Plan Review Days — City Control
14
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Queen Anne Neighborhood

Project Overview

Project Details
Value
$460,000
Type
Residential Construction
Issued
May 28, 2026
Location
Queen Anne

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct exterior alterations to existing multi-family building per plan

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Multifamily
Parcel
DV0029544
Review cycles
2
Plan review days
49
Days in corrections
14
Units added
0
Units removed
0
Open Map