PERMIT #7124768-CN
1201 NE CAMPUS PKWY, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
February 19, 2026
In Review
2 cycles
Reviews Done
May 22, 2026
Ready to Issue
May 26, 2026
Issued
May 26, 2026
Completed
—
Expires
November 26, 2027
92
Plan Review Days — Total
21
Plan Review Days — City Control
71
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1201 NE CAMPUS PKWY, SEATTLE, WA Property
MASTEC NETWORK SOLUTIONS INC Contractor
Wallingford Neighborhood
Project Overview
Project Details
Value
$30,000
Type
Commercial Construction
Issued
May 26, 2026
Location
Wallingford
Contractor Information
Location & Map
Project Description
AT&T SA1219 University Bridge Relo - LTE 1C RRH SWAP Construct alterations to minor telecommunications facility (AT&T) on rooftop of existing residential building (UW Landers Hall), per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MASTENS876KN
Review level
Full +
Primary use
Institutional
Parcel
DV0065844
Review cycles
2
Plan review days
92
Days in corrections
71
Expires
November 26, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0