PERMIT #7124917-CN

928 19TH AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
February 13, 2026
In Review
3 cycles
Reviews Done
April 1, 2026
Ready to Issue
April 1, 2026
Issued
April 2, 2026
Completed
Expires
October 2, 2027
47
Plan Review Days — Total
23
Plan Review Days — City Control
24
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$5,000
Type
Residential Construction
Issued
April 2, 2026
Location
Capitol Hill

Contractor Information

Contractor
BAER CONSTRUCTION INC
General Contractor
License BAERCCI941C3

Location & Map

Project Description
Construction Permit Construct hoistway from main floor to second floor for a home elevator in existing one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BAERCCI941C3
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1160333
Review cycles
3
Plan review days
47
Days in corrections
24
Expires
October 2, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor