PERMIT #7125720-CN
811 29TH AVE E, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 20, 2026
In Review
0 cycles
Reviews Done
April 21, 2026
Ready to Issue
April 21, 2026
Issued
April 21, 2026
Completed
—
Expires
October 21, 2027
91
Plan Review Days — Total
91
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$624,873
Type
Residential Construction
Issued
April 21, 2026
Location
Madison Valley
Contractor Information
Location & Map
Project Description
807 29th Ave E - PASV Construct west two-family dwelling BLDG B, per plan. (Establish use as townhouse, per land use code. Construct 2 new two-family dwellings, per plan. Review and processing for two records under 7109885-CN)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MIRRAHL817LK
Review level
Dependent Building
Primary use
Multifamily
Parcel
DV0018656
Review cycles
0
Plan review days
91
Days in corrections
0
Expires
October 21, 2027
Existing units
1
Units added
4
Units removed
1
Sleeping rooms
12