PERMIT #7125987-BK

2001 8TH AVE, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
January 22, 2026
In Review
2 cycles
Reviews Done
March 10, 2026
Ready to Issue
March 11, 2026
Issued
March 18, 2026
Completed
July 27, 2026
Expires
September 18, 2027
47
Plan Review Days — Total
19
Plan Review Days — City Control
28
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$1,261,180
Type
Commercial Construction
Issued
March 18, 2026
Location
Downtown

Contractor Information

Contractor
FOUSHEE & ASSOCIATES CO INC
General Contractor
License FOUSHAC158OD

Location & Map

Project Description
2001 8th Avenue - 16th Floor Construct blanket permit tenant improvements to Rippling on the 16th floor of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
FOUSHAC158OD
Review level
Full C
Primary use
Commercial
Parcel
DV0065039
Review cycles
2
Plan review days
47
Days in corrections
28
Expires
September 18, 2027
Open official SDCI detail →
View Contractor