PERMIT #7126412-CN

1911 46TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 27, 2026
In Review
2 cycles
Reviews Done
June 9, 2026
Ready to Issue
June 9, 2026
Issued
June 10, 2026
Completed
Expires
43
Plan Review Days — Total
33
Plan Review Days — City Control
10
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$40,000
Type
Residential Construction
Issued
June 10, 2026
Location
West Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Basement Remodel Construct alterations to existing one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1179265
Review cycles
2
Plan review days
43
Days in corrections
10
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →