PERMIT #7126488-CN
14076 22ND AVE NE, SEATTLE, WA
newPermit Timeline & Status
Construction Permit Timeline
Applied
May 21, 2026
In Review
3 cycles
Reviews Done
July 22, 2026
Issued
—
Completed
—
Expires
—
62
Plan Review Days — Total
34
Plan Review Days — City Control
28
Days in Applicant Control
3
Review Cycles
In City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
14076 22ND AVE NE, SEATTLE, WA Property
Pinehurst Neighborhood
Project Overview
Project Details
Value
$223,140
Type
Residential Construction
Issued
N/A
Location
Pinehurst
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
14074 22nd Ave NE Allow housing for one new detached dwelling unit, per land use code. Existing detached dwelling to remain. Construct new one-family dwelling, per standard plan 6880596-SP. Existing detached garage to be removed.
Additional Details
Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1177432
Review cycles
3
Plan review days
62
Days in corrections
28
Units added
1
Units removed
0