PERMIT #7126559-BK
1301 5TH AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 28, 2026
In Review
3 cycles
Reviews Done
March 10, 2026
Ready to Issue
April 8, 2026
Issued
May 5, 2026
Completed
—
Expires
November 5, 2027
41
Plan Review Days — Total
32
Plan Review Days — City Control
9
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$3,600,000
Type
Commercial Construction
Issued
May 5, 2026
Location
Downtown
Contractor Information
Location & Map
Project Description
Milliman Construct blanket permit tenant improvements to Milliman on floors 36-39 of existing commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
UNIMACL801B4
Review level
Full C
Primary use
Commercial
Parcel
DV0029706
Review cycles
3
Plan review days
41
Days in corrections
9
Expires
November 5, 2027