PERMIT #7126584-CN

716 W LEE ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
March 27, 2026
In Review
2 cycles
Reviews Done
May 15, 2026
Ready to Issue
May 18, 2026
Issued
July 24, 2026
Completed
Expires
49
Plan Review Days — Total
34
Plan Review Days — City Control
15
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Queen Anne Neighborhood

Project Overview

Project Details
Value
$456,591
Type
Residential Construction
Issued
July 24, 2026
Location
Queen Anne

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Establish use as housing for one detached dwelling units per land use code. Existing one family dwelling to remain. Construct new one family dwelling per plan. Project includes removal of detached garage.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0351898
Review cycles
2
Plan review days
49
Days in corrections
15
Units added
1
Units removed
0
Open Map