PERMIT #7126716-CN
318 NICKERSON ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
May 21, 2026
In Review
2 cycles
Reviews Done
June 25, 2026
Ready to Issue
June 26, 2026
Issued
June 29, 2026
Completed
—
Expires
—
35
Plan Review Days — Total
33
Plan Review Days — City Control
2
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$100,000
Type
Commercial Construction
Issued
June 29, 2026
Location
Queen Anne
Contractor Information
Location & Map
Project Description
Construction Permit Initial tenant improvement in a mixed-use building on ground floor, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CHAINCL825NU
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0093990
Review cycles
2
Plan review days
35
Days in corrections
2
Units added
0
Units removed
0