PERMIT #7126770-CN

370 LYNN ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
March 31, 2026
In Review
0 cycles
Reviews Done
May 27, 2026
Ready to Issue
May 29, 2026
Issued
May 29, 2026
Completed
Expires
57
Plan Review Days — Total
57
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Queen Anne Neighborhood

Project Overview

Project Details
Value
$656,520
Type
Residential Construction
Issued
May 29, 2026
Location
Queen Anne

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new WEST two family dwelling (THs 2A & 2B) per plan. (Establish use as housing for two attached dwelling units per land use code. Construct (2) new two family dwellings per plan. Review and processing for two records under 7119455-CN).

Additional Details

Permit Intelligence
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1174877
Related land-use permit
3043695-LU
Review cycles
0
Plan review days
57
Days in corrections
0
Units added
2
Units removed
0
Open Map