PERMIT #7127129-CN
3430 EAST MARGINAL WAY S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
March 27, 2026
In Review
2 cycles
Reviews Done
April 17, 2026
Ready to Issue
April 17, 2026
Issued
April 17, 2026
Completed
—
Expires
October 17, 2027
21
Plan Review Days — Total
20
Plan Review Days — City Control
1
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
LATU CONCRETE DESIGN Contractor
SoDo Neighborhood
Project Overview
Project Details
Value
$84,000
Type
Industrial Construction
Issued
April 17, 2026
Location
SoDo
Contractor Information
Location & Map
Project Description
Concrete Pour We are replacing 10,750 sqft of asphalt with 6" thick concrete inside our warehouse in 2 phases.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
LATUCCD816JZ
Review level
Full +
Primary use
Industrial
Parcel
DV0071559
Review cycles
2
Plan review days
21
Days in corrections
1
Expires
October 17, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0