PERMIT #7127339-CN

1109 41ST AVE E, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
February 16, 2026
In Review
3 cycles
Reviews Done
April 6, 2026
Ready to Issue
April 6, 2026
Issued
April 6, 2026
Completed
Expires
October 6, 2027
49
Plan Review Days — Total
37
Plan Review Days — City Control
12
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$195,000
Type
Residential Construction
Issued
April 6, 2026
Location
Other Seattle

Contractor Information

Contractor
THE MCKINNEY GROUP INC
General Contractor
License MCKINGI953CZ

Location & Map

Project Description
Roy Swimming Pool Construct pool and retaining walls for existing one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MCKINGI953CZ
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0336659
Review cycles
3
Plan review days
49
Days in corrections
12
Expires
October 6, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor