PERMIT #7127570-CN

6050 EAST MARGINAL WAY S, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
May 20, 2026
In Review
1 cycle
Issued
Completed
Expires
48
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$23,097
Type
Commercial Construction
Issued
N/A
Location
Georgetown

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
6050 E Marginal Way Lithium Battery Storage BLDG TI Establish use as … per land use code. Install new modified shipping container for battery storage, mechanical included per plan.

Additional Details

Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0088191
Review cycles
1
Days in corrections
48
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →