PERMIT #7128799-CN

9417 CALIFORNIA AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
May 26, 2026
In Review
2 cycles
Reviews Done
June 29, 2026
Ready to Issue
July 3, 2026
Issued
July 3, 2026
Completed
Expires
34
Plan Review Days — Total
22
Plan Review Days — City Control
12
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$100,000
Type
Residential Construction
Issued
July 3, 2026
Location
Other Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Loos-Delos Remodel Construct addition and alterations to existing one-family dwelling, per plan.

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0082548
Review cycles
2
Plan review days
34
Days in corrections
12
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
3
Open official SDCI detail →
Open Map