PERMIT #7130052-CN

3311 NE 60TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
May 28, 2026
In Review
2 cycles
Reviews Done
July 8, 2026
Ready to Issue
July 8, 2026
Issued
July 9, 2026
Completed
Expires
41
Plan Review Days — Total
31
Plan Review Days — City Control
10
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ravenna Neighborhood

Project Overview

Project Details
Value
$425,000
Type
Commercial Construction
Issued
July 9, 2026
Location
Ravenna

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct alterations to existing school building (Bryant Elementary) per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Institutional
Parcel
DV0023831
Review cycles
2
Plan review days
41
Days in corrections
10
Units added
0
Units removed
0
Open Map