PERMIT #7130409-CN

2350 50th AVE SW, Seattle, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
February 22, 2026
In Review
0 cycles
Ready to Issue
February 22, 2026
Issued
February 22, 2026
Completed
February 27, 2026
Expires
August 22, 2027
0
Days in Applicant Control
0
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$2,700
Type
Residential Construction
Issued
February 22, 2026
Location
West Seattle

Contractor Information

Contractor
EVERGREEN SEISMIC LLC
General Contractor
License EVERGSL823JF

Location & Map

Project Description
Glick Retrofit Voluntary seismic retrofit upgrade to basement of SFR, per engineered plan set, STFI

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
EVERGSL823JF
Housing category
Single-Family Add/Alt
Review level
Field
Primary use
Single Family/Duplex
Parcel
DV0055939
Review cycles
0
Days in corrections
0
Expires
August 22, 2027
Open official SDCI detail →