PERMIT #7130812-BK
701 5TH AVE, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
February 27, 2026
In Review
1 cycle
Reviews Done
March 10, 2026
Ready to Issue
March 11, 2026
Issued
March 17, 2026
Completed
May 21, 2026
Expires
September 17, 2027
11
Plan Review Days — Total
11
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$180,000
Type
Commercial Construction
Issued
March 17, 2026
Location
Downtown
Contractor Information
Location & Map
Project Description
Davis Grimm Construct blanket permit tenant improvements to Davis Grimm on the 35th floor of existing commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
JECUMC*148JH
Review level
Full C
Primary use
Commercial
Parcel
DV0029700
Review cycles
1
Plan review days
11
Days in corrections
0
Expires
September 17, 2027