Applied
February 26, 2026
In Review
0 cycles
Ready to Issue
March 3, 2026
Issued
March 3, 2026
Completed
Expires
September 3, 2027
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$5,000
Type
Residential Construction
Issued
March 3, 2026
Location
Capitol Hill

Contractor Information

Contractor
HILGER CONSTRUCTION INC
General Contractor
License HILGECI033QK

Location & Map

Project Description
25013 Silvian Construct interior alterations to unit 103 and replacement of finishes and cabs in other units in existing multifamily building, subject to field inspection (STFI).

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HILGECI033QK
Review level
Field
Primary use
Multifamily
Parcel
DV0003135
Review cycles
0
Days in corrections
0
Expires
September 3, 2027
Existing units
32
Units added
0
Units removed
0
Sleeping rooms
0