PERMIT #7131175-CN

605 EASTLAKE AVE E, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
July 8, 2026
In Review
1 cycle
Reviews Done
July 17, 2026
Ready to Issue
July 22, 2026
Issued
Completed
Expires
9
Plan Review Days — Total
9
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$1,500
Type
Residential Construction
Issued
N/A
Location
South Lake Union

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct tenant improvement for commercial space (Bike Swift) on ground floor at suite 603 & 605 of existing mixed-use building per plan.

Additional Details

Permit Intelligence
Review cycles
1
Plan review days
9
Days in corrections
0
Units added
0
Units removed
0
Open Map