PERMIT #7132163-CN

10217 12TH AVE NE, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
March 5, 2026
In Review
0 cycles
Reviews Done
May 27, 2026
Ready to Issue
May 28, 2026
Issued
Completed
Expires
83
Plan Review Days — Total
83
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Maple Leaf Neighborhood

Project Overview

Project Details
Value
$322,117
Type
Residential Construction
Issued
N/A
Location
Maple Leaf

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new one-family dwelling (SFR2) per plan. (Establish use for 2 attached dwelling units and 2 one-family dwellings per land use code Construct (2) one-family and (1) two-family dwellings per plan. Review and processing for two records under 7120176-CN)

Additional Details

Permit Intelligence
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1199570
Review cycles
0
Plan review days
83
Days in corrections
0