PERMIT #7132714-CN

11037 B 15TH AVE NE, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
March 10, 2026
In Review
0 cycles
Reviews Done
June 4, 2026
Ready to Issue
June 4, 2026
Issued
Completed
Expires
86
Plan Review Days — Total
86
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$244,576
Type
Residential Construction
Issued
N/A
Location
Maple Leaf

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct SOUTH one-family dwelling per plan. (Establish use as housing for two detached dwelling units per land use code. Existing detached dwelling to remain. Construct (2) new one-family dwellings and alterations to existing one-family dwelling per plan. Review and processing for (3) records under 7099168-CN.)

Additional Details

Permit Intelligence
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1158057
Review cycles
0
Plan review days
86
Days in corrections
0
Open Map