PERMIT #7133228-CN

1009 N 42ND ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
May 19, 2026
In Review
2 cycles
Reviews Done
July 9, 2026
Ready to Issue
July 9, 2026
Issued
July 9, 2026
Completed
Expires
51
Plan Review Days — Total
33
Plan Review Days — City Control
18
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Fremont Neighborhood

Project Overview

Project Details
Value
$100,000
Type
Residential Construction
Issued
July 9, 2026
Location
Fremont

Contractor Information

Contractor
THE GREEN BUILDER
General Contractor
License GREENGB797RB

Location & Map

Project Description
Home Addition Construct substantial alterations for two-story addition to existing one-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GREENGB797RB
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0023740
Review cycles
2
Plan review days
51
Days in corrections
18
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor