PERMIT #7133397-CN
801 1ST AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
March 27, 2026
In Review
1 cycle
Reviews Done
April 13, 2026
Ready to Issue
May 18, 2026
Issued
May 18, 2026
Completed
June 11, 2026
Expires
July 10, 2026
17
Plan Review Days — Total
17
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$100,000
Type
Commercial Construction
Issued
May 18, 2026
Location
SoDo
Contractor Information
Location & Map
Project Description
WOSCA Temporary Use Temporary use / permit for the WOSCA site to be used as charter bus staging for the FIFA World Cup, June -July 2026. Scope of work will include bicycle racks for parking, security fences, gates and temporary traffic control stanchions for under 80 busses at this location.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MAMORC*190N6
Review level
Full +
Primary use
Commercial
Parcel
DV0015082
Review cycles
1
Plan review days
17
Days in corrections
0
Expires
July 10, 2026