PERMIT #7133856-CN
2301 E UNION ST, SEATTLE, WA
newPermit Timeline & Status
Construction Permit Timeline
Applied
April 16, 2026
In Review
2 cycles
Reviews Done
June 17, 2026
Ready to Issue
July 1, 2026
Issued
—
Completed
—
Expires
—
62
Plan Review Days — Total
47
Plan Review Days — City Control
15
Days in Applicant Control
2
Review Cycles
Plan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2301 E UNION ST, SEATTLE, WA Property
Capitol Hill Neighborhood
Project Overview
Project Details
Value
$400,000
Type
Residential Construction
Issued
N/A
Location
Capitol Hill
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Midtown Square Event Space TI Establish use as Entertainment Use at the first floor of existing commercial building, per land use code. Construct tenant improvements for event space at plaza level of a mixed-use building, occupy per plan.
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Multifamily
Parcel
DV0342939
Review cycles
2
Plan review days
62
Days in corrections
15
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0