PERMIT #7134097-CN

549 S DAWSON ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 7, 2026
In Review
2 cycles
Reviews Done
May 21, 2026
Ready to Issue
May 21, 2026
Issued
May 21, 2026
Completed
Expires
November 21, 2027
44
Plan Review Days — Total
25
Plan Review Days — City Control
19
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$84,500
Type
Commercial Construction
Issued
May 21, 2026
Location
Georgetown

Contractor Information

Contractor
NORTH WEST HANDLING SYS INC
General Contractor
License NORTHWH275JF

Location & Map

Project Description
549 S Dawson St - Construction - Johnson Barrow Racks Construct alterations to install pallet racking for commercial warehouse building [NET VERSANT WAREHOUSE], per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
NORTHWH275JF
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0001362
Review cycles
2
Plan review days
44
Days in corrections
19
Expires
November 21, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0