PERMIT #7134453-CN

3535 27TH PL W, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
June 4, 2026
In Review
3 cycles
Reviews Done
August 5, 2026
Ready to Issue
August 5, 2026
Issued
August 5, 2026
Completed
Expires
62
Plan Review Days — Total
33
Plan Review Days — City Control
29
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Magnolia Neighborhood

Project Overview

Project Details
Value
$35,000
Type
Residential Construction
Issued
August 5, 2026
Location
Magnolia

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct structural alterations to existing apartment building at 1st level per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Multifamily
Parcel
DV0363540
Review cycles
3
Plan review days
62
Days in corrections
29
Units added
0
Units removed
0
Open Map