PERMIT #7134474-CN

1057 S DIRECTOR ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 20, 2026
In Review
2 cycles
Reviews Done
June 10, 2026
Ready to Issue
June 10, 2026
Issued
June 11, 2026
Completed
Expires
51
Plan Review Days — Total
23
Plan Review Days — City Control
28
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
South Park Neighborhood

Project Overview

Project Details
Value
$25,750
Type
Commercial Construction
Issued
June 11, 2026
Location
South Park

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct minor alterations to site-built telecommunications facility (AT&T) per plan

Additional Details

Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0057026
Review cycles
2
Plan review days
51
Days in corrections
28
Units added
0
Units removed
0
Open Map