PERMIT #7134725-CN
7533 EARL AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
April 15, 2026
In Review
3 cycles
Reviews Done
July 28, 2026
Ready to Issue
July 29, 2026
Issued
July 29, 2026
Completed
—
Expires
—
104
Plan Review Days — Total
74
Plan Review Days — City Control
30
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
7533 EARL AVE NW, SEATTLE, WA Property
Demolition at 7533 EARL AVE NW Project
SEA HOME BUILDERS LLC Contractor
Ballard Neighborhood
Project Overview
Project Details
Value
$640,651
Type
Residential Construction
Issued
July 29, 2026
Location
Ballard
Contractor Information
Location & Map
Project Description
7533 Earl Ave NW, Seattle Establish use as housing for two attached dwelling units, per land use code. Construct new two-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SEAHOHB806DO
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1115517
Review cycles
3
Plan review days
104
Days in corrections
30
Existing units
1
Units added
2
Units removed
0
Sleeping rooms
5