Construction Permit Timeline
Applied
March 24, 2026
In Review
0 cycles
Ready to Issue
March 24, 2026
Issued
March 24, 2026
Completed
—
Expires
September 24, 2027
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
504 NE 95TH ST, SEATTLE, WA Property
Maple Leaf Neighborhood
Project Overview
Project Details
Value
$32,000
Type
Commercial Construction
Issued
March 24, 2026
Location
Maple Leaf
Contractor Information
Contractor
Not published by SDCI
License VALLEEC141NA
Location & Map
Project Description
Olympic View ES - AV Security Upgrades Construct security upgrades for Olympic View Elementary School, subject to field inspection (STFI).
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VALLEEC141NA
Review level
Field
Primary use
Institutional
Parcel
DV0031479
Review cycles
0
Days in corrections
0