PERMIT #7136018-CN
2101 N NORTHLAKE WAY, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
April 6, 2026
In Review
1 cycle
Reviews Done
April 13, 2026
Ready to Issue
April 14, 2026
Issued
April 14, 2026
Completed
June 15, 2026
Expires
October 14, 2027
7
Plan Review Days — Total
7
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$100,000
Type
Land
Issued
April 14, 2026
Location
Eastlake
Contractor Information
Location & Map
Project Description
Gas Works Park Partial Demolition Partial demolition/deconstruction of pedestrian appurtenances (ladders, catwalks and stairways, and associated supports) and removal of segment of elevated pipe connecting north and south cracking towers at Gasworks park, per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
LAMBCCL801JA
Review level
Full C
Primary use
Vacant Land
Parcel
DV0012219
Review cycles
1
Plan review days
7
Days in corrections
0
Expires
October 14, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0