PERMIT #7136307-CN

2874 30th Ave W, Seattle, WA

Active

John Kolosta Construct alterations to one family dwelling at basement at 2874 30th Ave W, Seattle, WA in Magnolia, Seattle. Permit 7136307-CN is active, valued at $10,000.

Permit Timeline & Status

Construction Permit Timeline
AppliedMay 6, 2026
In Review4 cycles
Reviews DoneAugust 24, 2026
Ready to IssueAugust 24, 2026
IssuedSeptember 1, 2026
Completed—
Expires—
110
Plan Review Days — Total
55
Plan Review Days — City Control
55
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Magnolia Neighborhood

Project Overview

Project Details
Value
$10,000
Type
Residential Construction
Issued
September 1, 2026
Location
Magnolia

Contractor Information

Contractor
Not published by SDCI

Location & Map

Development site
DV1188868
Site area
7,425 sq ft
Site status
ACTIVE
Source updated
May 19, 2026
Last checked
Nov 28, 2026

Current SDCI site context. The outline shows the development-site boundary used for code standards.

Official Seattle development-site data →
Project Description
John Kolosta Construct alterations to one family dwelling at basement, per plan.

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Property reference
DV1188868
Review cycles
4
Plan review days
110
Days in corrections
55
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →