PERMIT #7137604-CN
4122 3RD AVE NW, SEATTLE, WA
newPermit Timeline & Status
Construction Permit Timeline
Applied
May 18, 2026
In Review
1 cycle
Issued
—
Completed
—
Expires
—
57
Days in Applicant Control
1
Review Cycles
In City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$60,000
Type
Residential Construction
Issued
N/A
Location
Fremont
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Franzen Dormer Remodel Construct additions and alterations to upper floor of existing unit within existing triplex, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Multifamily
Parcel
DV0037154
Review cycles
1
Days in corrections
57
Existing units
3
Units added
0
Units removed
0
Sleeping rooms
3