PERMIT #7137676-CN

1616 EASTLAKE AVE E, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 22, 2026
In Review
3 cycles
Reviews Done
July 7, 2026
Ready to Issue
July 9, 2026
Issued
July 9, 2026
Completed
Expires
76
Plan Review Days — Total
40
Plan Review Days — City Control
36
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$78,212
Type
Commercial Construction
Issued
July 9, 2026
Location
Capitol Hill

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construction Permit - glass washing station updates Tenant improvements for laboratory at level 3 room 3900 of existing commercial building, per plan.

Additional Details

Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0059768
Review cycles
3
Plan review days
76
Days in corrections
36
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →