PERMIT #7137827-CN
4202 43RD AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
May 21, 2026
In Review
2 cycles
Reviews Done
July 6, 2026
Ready to Issue
July 7, 2026
Issued
July 7, 2026
Completed
—
Expires
—
46
Plan Review Days — Total
30
Plan Review Days — City Control
16
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
4202 43RD AVE NE, SEATTLE, WA Property
Addition at 4202 43RD AVE NE Project
COMPLETE CONST & REMODEL LLC Contractor
Other Seattle Neighborhood
Project Overview
Project Details
Value
$451,676
Type
Residential Construction
Issued
July 7, 2026
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Harris Stowell Remodel Construct addition and substantial alterations to existing one family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
COMPLCR802BZ
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0094716
Review cycles
2
Plan review days
46
Days in corrections
16
Units added
0
Units removed
0