PERMIT #7138867-CN
14049 1ST AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
May 13, 2026
In Review
2 cycles
Reviews Done
June 18, 2026
Ready to Issue
June 22, 2026
Issued
June 22, 2026
Completed
—
Expires
—
36
Plan Review Days — Total
23
Plan Review Days — City Control
13
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$222,214
Type
Residential Construction
Issued
June 22, 2026
Location
Broadview
Contractor Information
Location & Map
Project Description
Construction Permit - New DADU Standard Plan Allow housing for one new detached dwelling unit, per land use code. Existing detached dwelling to remain. Construct new one-family dwelling, per standard plan 6880596-SP.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MTTCOCL866KT
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV0012966
Review cycles
2
Plan review days
36
Days in corrections
13
Units added
1
Units removed
0