PERMIT #7139458-CN
3823 35TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
April 21, 2026
In Review
2 cycles
Reviews Done
June 2, 2026
Ready to Issue
June 2, 2026
Issued
June 2, 2026
Completed
—
Expires
—
42
Plan Review Days — Total
31
Plan Review Days — City Control
11
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
3823 35TH AVE W, SEATTLE, WA Property
Magnolia Neighborhood
Project Overview
Project Details
Value
$185,917
Type
Residential Construction
Issued
June 2, 2026
Location
Magnolia
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Panesat PADADU Allow housing for one new detached dwelling unit per the land use code, existing detached dwelling to remain (no work). Construct new one-family dwelling, per standard plan 6794017-SP .
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1202272
Review cycles
2
Plan review days
42
Days in corrections
11
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0