PERMIT #7140567-CN

207 BOREN AVE N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 29, 2026
In Review
0 cycles
Ready to Issue
April 30, 2026
Issued
April 30, 2026
Completed
Expires
October 30, 2027
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$7,500
Type
Commercial Construction
Issued
April 30, 2026
Location
South Lake Union

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
29TW092604 Construct Tenant improvement Project at 207 Boren Ave N. Removing existing partial-height demoutable partitions and installing full-height demountable partition walls, subject to field inspection, STFI.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Commercial Add/Alt
Review level
Field
Primary use
Commercial
Parcel
DV0073568
Review cycles
0
Days in corrections
0
Expires
October 30, 2027
Open official SDCI detail →