PERMIT #7141155-CN

4659 25TH AVE NE, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
June 2, 2026
In Review
1 cycle
Issued
Completed
Expires
47
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
University District Neighborhood

Project Overview

Project Details
Value
$327,728
Type
Commercial Construction
Issued
N/A
Location
University District

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct alterations for UW car wash oil-water separator accessory to existing UW Facilities Services Building per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Institutional
Parcel
DV0059241
Review cycles
1
Days in corrections
47
Units added
0
Units removed
0
Open Map