PERMIT #7143639-BK

600 UNIVERSITY ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
May 20, 2026
In Review
2 cycles
Reviews Done
July 8, 2026
Ready to Issue
July 8, 2026
Issued
July 8, 2026
Completed
Expires
49
Plan Review Days — Total
15
Plan Review Days — City Control
34
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$4,752,065
Type
Commercial Construction
Issued
July 8, 2026
Location
Downtown

Contractor Information

Contractor
SKYLINE CONSTRUCTION
Commercial
License SKYLIC*773DW

Location & Map

Project Description
OUS Floors 35 & 36 Arnold & Porter Construct blanket permit tenant improvements to Arnold & Porter Seattle on the 35th and 36th floors of existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SKYLIC*773DW
Review level
Full C
Primary use
Commercial
Parcel
DV0009533
Review cycles
2
Plan review days
49
Days in corrections
34
Open official SDCI detail →
View Contractor