PERMIT #7144578-DM
325 DENNY WAY, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
June 8, 2026
In Review
2 cycles
Reviews Done
June 26, 2026
Ready to Issue
June 29, 2026
Issued
July 2, 2026
Completed
—
Expires
—
18
Plan Review Days — Total
18
Plan Review Days — City Control
0
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$500,000
Type
Land
Issued
July 2, 2026
Location
Belltown
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Demolish existing commercial building per plan.
Additional Details
Permit Intelligence
Review level
Full +
Primary use
Vacant Land
Parcel
DV0060098
Review cycles
2
Plan review days
18
Days in corrections
0
Units added
0
Units removed
0