PERMIT #7145487-BK
2001 8TH AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
June 1, 2026
In Review
2 cycles
Reviews Done
June 27, 2026
Ready to Issue
June 29, 2026
Issued
July 6, 2026
Completed
—
Expires
—
26
Plan Review Days — Total
19
Plan Review Days — City Control
7
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$2,400,000
Type
Commercial Construction
Issued
July 6, 2026
Location
Downtown
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct blanket permit tenant improvements to General Motors on the 11th and 12th floors of existing commercial building per plan.
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Commercial
Parcel
DV0065039
Review cycles
2
Plan review days
26
Days in corrections
7