PERMIT #7145753-CN

701 5TH AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
June 1, 2026
In Review
0 cycles
Ready to Issue
June 2, 2026
Issued
June 3, 2026
Completed
Expires
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$22,500
Type
Commercial Construction
Issued
June 3, 2026
Location
Downtown

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct interior alterations to existing tenant space subject to field inspection STFI.

Additional Details

Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Field
Primary use
Commercial
Parcel
DV0029700
Review cycles
0
Days in corrections
0