PERMIT #7146005-CN

12544 25TH AVE NE, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
June 3, 2026
In Review
0 cycles
Ready to Issue
June 3, 2026
Issued
June 3, 2026
Completed
July 23, 2026
Expires
0
Days in Applicant Control
0
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Pinehurst Neighborhood

Project Overview

Project Details
Value
$40,000
Type
Residential Construction
Issued
June 3, 2026
Location
Pinehurst

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct alterations to a one-family dwelling subject to field inspection (STFI)

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Field
Primary use
Single Family/Duplex
Parcel
DV0091629
Review cycles
0
Days in corrections
0
Open Map